How Long Does a Kitchen Remodel Actually Take?

A real timeline from John Whitmoyer, owner of CSI. No best case fairy tales.

Every homeowner asks the same first question. How long are you going to be in my house? Most contractors answer with the best case scenario, then watch it slip. I would rather give you the real number and beat it than give you a fairy tale and disappoint you.

Here is a real Indianapolis kitchen timeline, phase by phase, with the parts that actually run long.

Before Demo Day: 4 to 8 Weeks

The clock starts way before anyone swings a hammer. This is the part most homeowners underestimate.

  • Design and layout decisions: 1 to 2 weeks.
  • Cabinet selection, measuring, and order: 1 week to select, then 4 to 10 weeks lead time depending on line. Custom cabinets in 2026 are the single biggest variable in any kitchen schedule.
  • Countertop template (happens after cabinets are in place, not before).
  • Permits with the City of Indianapolis: 1 to 3 weeks.

Anyone who tells you they can start demo next week is either using stock cabinets they have on hand, or they are about to leave you with a torn up kitchen waiting on a cabinet truck.

Week 1: Demo and Rough In

Cabinets out, appliances out, flooring up if it is being replaced. Then framing changes, plumbing rough in, electrical rough in, HVAC adjustments. If walls are coming down or the layout is changing, this is when the surprises show up: bad wiring, leaking shutoffs, rot under the sink, asbestos tile under the linoleum.

Week 2: Inspections and Drywall

Rough in inspections happen before walls close up. Then insulation, drywall, mud, sand. Drywall is the dustiest phase. We tarp off the rest of the house so the rest of your life keeps going.

Weeks 3 to 4: Flooring, Paint, Cabinets

Flooring goes in first if it is tile or hardwood that needs to run under the cabinets, or after cabinets if it is luxury vinyl plank or floating. Paint usually goes on the walls before cabinets are set so cutting in is clean. Cabinets get installed, leveled, and shimmed. This is the week the kitchen starts to look like a kitchen again.

Weeks 5 to 6: Countertop Template, Fabrication, Install

Countertops cannot be templated until cabinets are set. Templating takes a couple of hours. Fabrication takes one to two weeks. Install is one day. There is no shortcut on this and it is one of the most common places homeowners ask why we are waiting. We are waiting on the shop, not the slab.

Weeks 7 to 8: Tile, Trim, Plumbing, Electrical Trim Out

Backsplash tile after countertops. Sink, faucet, garbage disposal, dishwasher hookup, range and hood install. Outlets and switches trimmed out, light fixtures hung, under cabinet lighting wired. Trim work, hardware, paint touch ups.

Week 9: Final Inspection and Walkthrough

Final inspection with the city. Punch list walkthrough. Anything that is not perfect gets fixed before we are done. Final clean. Hand you the keys to your new kitchen.

Realistic Timelines by Project Type

  • Cosmetic refresh (paint, hardware, fixtures, no layout change): 2 to 3 weeks.
  • Standard remodel (new cabinets in same layout, new countertops, new appliances): 6 to 10 weeks once materials arrive.
  • Full gut with custom cabinets and moved walls: 10 to 16 weeks once materials arrive.
  • Add 4 to 10 weeks on top of those for design, ordering, and cabinet lead time before demo day.

Where Projects Actually Run Long

  • Cabinet lead times. Order early and stick to your decisions.
  • Stone slab fabrication. The shop has its own schedule.
  • Backordered appliances. Confirm in stock dates before you start.
  • Mid project change orders. Every layout change after demo restarts the clock on something.

The contractors who finish on time are the ones who finish their decisions before demo day. The ones who run late are the ones who keep changing their minds.

Ready to Plan Yours?

If you want a real timeline based on your actual kitchen, I will come walk it with you. For a budget breakdown, read our kitchen remodel cost guide. Before you sign with anyone, read our guide to choosing an Indianapolis remodeler.